Monday, 26 June 2017

Kitchen


Well, here is the kitchen about a week ago. The work has started. Added in a photo of the last time we had Navs in our kitchen before the end of term - when there is no stuff in it the kitchen looks TINY!

Here's the update:
Planning permission
Well, it's not the answer that I wanted, but that whole morning of phoning up the council, planning permission, structural engineers did lead us to conclude that all the structural work HAS BEEN accepted by the council already, and it's tiny corrections we are waiting for. Hence the builders can do lots of the work. So it's not the answer to prayer I wanted, but it's what we needed - we can go ahead with the work.

Electric meter
I have only praise for Scottish Power, they have been excellent. In touch with Alan about moving the meter and the dates they have offered is a visit on the 13th of July and we are booked in for the 20th. We are marked as 'urgent' if there are cancellations. I'll call up today and see if there are any. I reckon if we have to wait till the 20th the work may take at least 2 more weeks than planned (so the baby would definitely be born while we are at the Manners). In some ways, I've done all I can so am just waiting to see if we get a cancellation. Asking doesn't seem as urgent anymore, and I doubt we will get a cancellation so have stopped asking for it. But it would really be good to get a date sooner. I'll tell our contractor the news today and see what he says (I'm afraid they will pause the work and go elsewhere till the meter is moved...!).

Love living at the Manners. We had our show on Saturday evening and it was a blast. There has been so much blessing. Lots of reasons to be anxious, lots of reasons to be thankful. I don't want to just focus on anxieties and forget thanksgiving. Thanks for following this progress.

Friday, 16 June 2017

Kitchen

Hello and thanks for following the kitchen tales.

This has already happened:
- The builders can go ahead despite the meter being moved.

This is yet to happen:
- Edinburgh City Council gives us the go-ahead early this week.
- We get our meter moved this or next week.

We have already moved out and into the Manners house which is lovely. Our flat is empty and ready for the builders to start.

PERMISSION FROM THE COUNCIL
I chased up the city council yesterday and had a distressing morning of being told several things:
1) our job was only submitted on the 9th of June, they have a backlog so we should wait till July before we get permission. I spoke to manager Glen about this and he said we couldn't skip the queue.
2) the man doing our job is on long term sick leave which is why it hadn't been delegated
3) the man it was delegated onto after the second submission is on holiday...
4) I called Glen around 9am, and after all the above was discovered, I called him again at 11:30am and I think I was given favour with him, as he said he got one of his guys to pull out our file, and have a look at it, and if it was straightforward he would grant us permission. So THAT is great news. Not heard back from him yet though.
HOWEVER, after talking to our builder and architect (Ben did this bit) we discovered that the first submission to the council (which was accepted bar some minor things like: plastic covers on the edges of cabinets) HAS been accepted. Therefore all the structural work has been approved by the council. Apparently this happens all the time; the big aspects of the job are fine but the council says 'add a fence' and then you have to resubmit with the fence included; but most builders start the work before the second submission arrives; which is what we are going for.

.... All of this being said, I am sitting in the flat because of a visit from a mortgage guy and despite being able to go ahead with the work, there has been no sign of our builders (who were meant to be tearing out the kitchen yesterday)...

ELECTRIC METER
Well, all my calling has resulted in the job being labelled 'urgent'. Hooray!
Got a call from the guy in charge of the deliveries team (Sean) and Alan will be the guy that comes to fit it. Sean offered me a 3 week period; I explained the circumstances and said I was willing to call every day to see if there was a cancellation. Everyone at SP Energy networks (Scottish Power) has been really great. Sean told me Alan is on holiday today but will be back and should be in touch Mon/Tues so I will hold my phone-fire and not call until then. Keep praying it would be done sooner. Our builders also have to build part of a new wall that the electric meter will be moved to; but chances are that will happen well before the meter is moved. Fun and games, but progress.

I am very thankful. Hoping to hear back from the council today. Thanks for your prayers.

On another note, I was told by Ros my supervisor to take an extra week of maternity leave off (so I will be finishing work end of June) AND to only work half time for the next two weeks (other half mat leave) which gives me time to do kitchen stuff. I gladly accepted. But even though yesterday and today I am 'off' - I am still hanging out with some of the girls before they head off home.Thanks for reading!

Tuesday, 13 June 2017

Kitchen

Ok here were my hopes from last time:
- Edinburgh City Council gives us the go-ahead early this week.
- We get our meter moved this or next week.
- The builders can go ahead despite the meter being moved.

So far, the third has happened! The builders are coming in at 8am on Thursday and will start tearing out the old kitchen and doing what they can till we get permission. And they will knock down walls but only do so much before they need the electric meter moved. So we will finalise packing and move out tomorrow (hooray!)

Really really really want the council to give us permission ASAP. Going ahead without permission is possible (a £70 fine doesn't seem to bad) but we would rather do this well. I am bypassing my architect and going straight to the building warrant folks tomorrow. In between calling them I will be calling the electric meter people. I've called them pretty much every day since Thursday past apart from the weekend and we are slowly moving through the process of application, quote, acceptance, payment and at 3pm tomorrow I will phone the connections team and beg them to come and carry out the move asap.

Glad to be moving out the flat though, it'll feel like a big step in the right direction.
Aunty Louise came over and helped pack stuff this afternoon, and will tomorrow which is a great help!

Monday, 12 June 2017

Kitchen progress

So its Monday 12th June. And work was optimistically meant to start today. However, we are still in our flat (most of our stuff is packed away and if we had to get out tonight, we could easily do so) - thanks to Ben and MANY friends who helped him while I was away.

Moving our electric meter (on a wall which needs to be knocked down) may take 4 weeks to move! I am praying for a cancellation or a slot when we can move it much before then. Still not heard back from the council with permission, and trying to get in touch with our builder to see what's going to happen.

It is good to remember that God has provided for our needs so far, is in control of this situation. Its a joy to be able to trust him BEFORE things seems to be going as we wished. We trust it will be ok, regardless of circumstances.

Here are my hopes though:
- Edinburgh City Council gives us the go-ahead early this week.
- We get our meter moved this or next week.
- The builders can go ahead despite the meter being moved.

Will keep you posted!